January 2006
Walls rise on nearly 30 homes. Installation begins on drainage systems around homes.
March 2006
30 "turn key" homes completed.
April 2006
6 additional houses awarded to the contractor. 36 homes presented at the Handover Ceremony on April 30th.
May 2006
6 more homes completed. Electricity and water supply obtained for all homes.
June 2006
GTZ has selected our homes for two publications titled "Innovative Technology Towards Sustainability - Building Practices on Post Tsunami Housing" and "Participatory Practices on Post Tsunami Development"
July 2006
Completed fencing along the main road and the by lanes.
August 2006
Construction begins on 4 more houses managed and supervised by Colliers Kirinda Trust.
November 2006
External kitchen and shop added.
December 2006
Four more houses completed.